Our Works
LLC «Sawing and woodworking industrial complex №2» (Russia, the Vologda area)
6/05/2009 – 7/20/2010
Technology equipment dismantle of second-hand lines of saw-timbers sorting, ancillary equipment, the equipment of support and carrying metalware of the saw-timbers sorting workshop, situated in the Kingdom of Sweden (ANIMSCOG), sawing factory «Tom Heurlin AB» (Moelven group), purchased by the Customer from the firm UJ Trading AB (Moelven group).
- Drawing up the wiring diagrams of mechanical, pneumatic, hydraulic parts of lines and dismantled units of the electric power and electronic parts of a line
- drawing up the layout charts of a line and workshop support metalware; detailed photos of all main line constructions, units, wires and aggregates
- marking of all separate dismantled parts of a line; study of the electronic system of the line control, instructions on loading of the data in the PC for saw-timbers sorting routines. Preparation of the line dismantled parts for loading, including
- optimal configuration of the dismantled parts in separate transport places (holders) with necessary fixing and package
- marking of all separate transport places and packing sheets with indications of all separate parts included in a transport place
Loading of the equipment and the workshop metalware on motor transport in the Kingdom of Sweden, executing of packing documents on each motor vehicle, handing them over to the Seller for the transport documents executing.
Joint-Stock Company «Forest - Grand» (Russia, Tver)
4/27/2009-05/15/2009
Installation of supporting poles and pipelaying of a heat pipeline
5/16/2009 – 5/30/2009
Mounting of a Packaging line metalware
6/1/2009 – 7/5/2009
Mounting of a wood chips cutting line
«ASSK» (LATVIYA)
02/10/2009 – 03/10/2009
Rendering of technical consultation on installation and a packaging arrangement of the woodworking equipment, drawing up schemes of the given equipment (electric and erection facilities).
04/01/2009 – 05/01/2009
The mounting of a Packaging Machine on the territory of Russia in Tver
LLC “Terminal VN” (Russia, Velikiy Novgorod)
09/29/2008 – 10/08/2008
Drawing up of the project schemesaw-timbers sorting line according the given documents
Joint-Stock Company "КАТА" (Russia, Irkutsk region)
8/25/2008 – 10/10/2008
Mounting of a mechanical part of two second-hand saw-timbers packing lines on the woodworking shop under construction in Ust-Ilimsk.
LLC «Amur Forest» (Russia, Khabarovsk krai)
01/16/2008 – 05/10/2008
Drawing up necessary schemes of the equipment, i.e. sawlog and saw timber sorting line, situated in the states of Germany and Finland. The assembly drawing of an electric part of a line, the drawing of support beams on the operating plate of the base according to a zero mark, the schematical drawing of the line dismantled units disposition and distances, drawing up the specification of the dismantled equipment. Taking of the second-hand equipment in working condition, staff training for the later starting-up and adjustment works of the given line. Drawing up the specification for the shipment and customs clearance of the given line, loading according to the made specification and packing list drawing up, marking of the equipment according to the specification, carrying out the complete photographical report of the shipped equipment necessary for the further installation.
06/10/2008 – 02/24/2009
Installation of the saw-timbers sorting line on the territory of Russia in Khabarovsk krai, carrying out the step-by-step photographical report of the done work.
LLC «Novgorodskaja Lesopromishlennaja Companija "Sodrujestvo"(Russia, the Novgorod region)
06/28/2007 – 03/31/2008
Installation of the mechanical and electric parts of the second-hand saw-timber sorting line, preparation of the base for the given line installation, manufacturing and installation of the equipment necessary for high-grade working capacity of the given line, carrying out the line reconstruction for the increase in final volume, carrying out the starting-up and adjustment works.
TrateknikByran AB (SWEDEN)
08/12/2007 – 12/31/2007
Dismantle of the saw-timbers sorting line in the Kingdom of Sweden (GLIMAKRA), drawing up an assembly and electric schemes to the given line, compiling the drawing of the bearing support (according to a zero mark), drawing up the specification for shipment and customs clearance of the given line, loading according to the made specification and packing list drawing up, marking of the equipment according to the specification, carrying out the complete photographical report of the shipped equipment necessary for the further installation of the equipment with a view of dismantled parts, the dismounted joints, the shipped equipment according to the packing list of each car and a line general view.
11/21/2007 – 12/21/2007
Dismantle of the saw-timbers packing line in the Kingdom of Sweden (EDSBYN), drawing up the necessary schemes for the equipment further installation, making the complete photographical report of done works, drawing up the specification for shipment and customs clearance of the given line, loading according to the made specification and packing list drawing up, marking of the equipment according to the specification
03/17/2009 – 04/10/2009
Dismantle of the splitting line in the Kingdom of Sweden, carrying out the complete photographical report necessary for the further installation and making the report of done works.
05/25/2009 – 06/14/2009
Installation of the splitting line on the territory of Russia.